PSM I Interactive Scenario Trainer — DIP Method Prototype

Learner View

  1. 1Detect
  2. 2Interpret
  3. 3Prioritize

During Day 6 of a 2-week Sprint, a key stakeholder approaches the Developers directly during lunch and asks them to add a 'small, urgent reporting widget' before the Sprint Review. Wanting to be helpful, two Developers start working on it without consulting the Product Owner or updating the Sprint Backlog. At the next Daily Scrum, progress on the Sprint Goal has stalled.

Step 1: Detect

What is the primary Scrum framework anti-pattern occurring in this situation?